Scope
18 floors · erection & bracing
Steel tower frame against the sky
Structural frame detail

DELIVERY

The frame was sequenced in six-floor lifts so that decking and bracing followed erection within one week. Connection plates were shop-fabricated and match-marked, cutting site welding to bracing nodes only. Crane time was shared with the adjacent facade package and coordinated on a daily lift plan.

  • Floors18
  • Steel tonnage2,400 t
  • Duration14 months
  • Peak workforce180