Concrete foundations

DEEP FOUNDATION WORKS

Bored piling and a heavily reinforced raft slab for a high-load industrial structure on variable ground.

Client
Industrial group
Location
Dammam, Saudi Arabia
Year
2024
Scope
Piling & raft slab
Foundation works and rebar cage

DELIVERY

Ground investigation drove a mixed solution: bored piles to competent strata under the core, spread footings elsewhere. The raft was poured in five continuous sections with temperature monitoring through the curing window.

  • Piles312
  • Concrete9,800 m³
  • Duration9 months
  • Lost-time incidents0